The Globe - Serving Gogebic, Iron and Ontonagon Counties

Ironwood performs water maintenance

 

June 16, 2021

Zachary Marano/Daily Globe

Construction crews excavate the blacktop at the intersection of Norrie Park and VanBuskirk roads to replace the water main underneath. The project started last week and is scheduled to be completed by July 2, Utilities Manager Bob Tervoven said.

by Zachary Marano

[email protected]

IRONWOOD - The city of Ironwood's utilities department started removing the blacktop on VanBuskirk Road between Pioneer Road and Normandy Avenue last week.

According to the city's Utilities Manager Bob Tervonen, VanBuskirk is being excavated to replace the water main under the road. He said that construction crew will replace 800 feet of the water main.

The city is also replacing the water main and sewer lines on West Pewabic Street, he said.

Tervonen said that city residents in these areas will experience periodic water service disruptions and d...



For access to this article please sign in or subscribe.

 
 

Powered by ROAR Online Publication Software from Lions Light Corporation
© Copyright 2023

Rendered 06/08/2023 08:48